The Year View shows all loaded tasks for a RadGantt distributed in columns that have duration of one month. Those columns are further grouped into years.

RadGantt in Year View

YearViewSettings Object

Table 1 demonstrates the properties that are available within the YearViewSettings object.

NameTypeDescription
MonthHeaderDateFormatstringGets or sets the month header date format string in YearView.
RangeEndDateTime?Gets or sets the end date and time of the visible range on the YearView. The RangeEnd date will not be included within the visible range.
RangeStartDateTime?Gets or sets the start date and time of the visible range on the YearView.
SelectedDateDateTime?Gets or sets the date and time to which the timeline of the YearView is scrolled.
SlotWidthUnitGets or sets the slot width in pixels for the YearView.
TypeTelerik.Web.UI.GanttViewType enumerationGets the type of the View. In this case a YearView.
UserSelectableboolGets or sets a value indicating whether to render a tab for the YearView in the view chooser.
YearHeaderDateFormatstringGets or sets the year header date format string in YearView.