The Week View shows all loaded tasks for a RadGantt distributed in columns that have duration of one day. Those columns are further grouped into weeks.

RadGantt in Week View

WeekViewSettings Object

Table 1 demonstrates the properties that are available within the WeekViewSettings object.

NameTypeDescription
DayHeaderDateFormatstringGets or sets the day header date format string in WeekView.
RangeEndDateTime?Gets or sets the end date and time of the visible range of the WeekView. The RangeEnd date will not be included within the visible range.
RangeStartDateTime?Gets or sets the start date and time of the visible range of the WeekView.
SelectedDateDateTime?Gets or sets the date and time to which the timeline of the WeekView is scrolled.
SlotWidthUnitGets or sets the slot width in pixels for the WeekView.
TypeTelerik.Web.UI.GanttViewType enumerationGets the type of the View. In this case a WeekView.
UserSelectableboolGets or sets a value indicating whether to render a tab for the WeekView in the view chooser.
WeekHeaderDateFormatstringGets or sets the week header date format string in WeekView.