This is a migrated thread and some comments may be shown as answers.

Scheduler DayView, stretching appointment in a way that force it to make EndDateTime same as StartDateTime

1 Answer 13 Views
Scheduler
This is a migrated thread and some comments may be shown as answers.
shailaja
Top achievements
Rank 1
shailaja asked on 17 Jan 2009, 08:33 AM
Hello,

In scheduler dayview, while stretching an appointment, currently it takes minimum 30 minutes gap between start and end. I have a scenario where I need to allow the user to stretch it in a way to force this gap as zero seconds and make its start and end equal. In our case, it is different than deleting an appointment.

Is it possible to implement this solution in present scheduler & how?

Thanks,
Shailaja

1 Answer, 1 is accepted

Sort by
0
Peter
Telerik team
answered on 19 Jan 2009, 02:54 PM
Hello shailaja,

The start time must be before the end time, otherwise the built-in validation in RadScheduler will fail.


Peter
the Telerik team

Check out Telerik Trainer, the state of the art learning tool for Telerik products.
Tags
Scheduler
Asked by
shailaja
Top achievements
Rank 1
Answers by
Peter
Telerik team
Share this question
or