Gantt Chart Dependent Tasks

1 Answer 39 Views
Gantt
Eric
Top achievements
Rank 1
Eric asked on 28 Oct 2024, 06:09 PM
In the gantt chart web client, when I shift one of the tasks that has a chain of dependent tasks below it, the dependencies don't shift the same number of days; I have to manually edit each one.

Am I missing something, or is this not a feature?

Thanks!

1 Answer, 1 is accepted

Sort by
0
Rumen
Telerik team
answered on 31 Oct 2024, 07:36 AM

Hi Eric,

The current behavior of the RadGantt control does not automatically update the dates of dependent tasks when the predecessor task's dates are changed. This feature is not built-in, and you would need to manually adjust the dates of dependent tasks.

There is a feature request related to this functionality, which suggests having an automatic update of successor task dates when the predecessor is modified. You can find more details about this request in our feedback portal and vote for raising its priority in the backlog:

https://feedback.telerik.com/aspnet-ajax/1376100-gantt

I recommend keeping an eye on the feedback portal for any updates regarding this feature.

    Regards,
    Rumen
    Progress Telerik

    Stay tuned by visiting our public roadmap and feedback portal pages! Or perhaps, if you are new to our Telerik family, check out our getting started resources