New to Telerik UI for ASP.NET AJAXStart a free 30-day trial

PDF Export

Updated on Aug 24, 2026

This help article explains how to enable and configure PDF Export for RadGantt.

Enable PDF Export

To enable the built-in PDF export functionality for RadGantt you should set its EnablePdfExport property to true:

ASP.NET
<telerik:RadGantt runat="server" ID="RadGantt1" 
	RenderMode="Lightweight" 
	Height="450px"
	SelectedView="MonthView"
	EnablePdfExport="true">
</telerik:RadGantt>

Enabling the above property will force the RadGantt to display an Export to PDF button on its toolbar:

gantt-export-button

Configure PDF Export

The PDF Export functionality is configurable. The RadGantt offers two ways to configure the export:

  • by using the properties of the ExportSettings > PDF element within the RadGantt mark-up declaration:
ASP.NET
<telerik:RadGantt runat="server" ID="RadGantt1" 
	RenderMode="Lightweight" 
	Height="450px"
	SelectedView="MonthView"
	EnablePdfExport="true">
	<ExportSettings>
		<Pdf
			FileName="GanttPDF"
			MarginBottom="10mm"
			MarginLeft="10mm"
			MarginRight="10mm"
			MarginTop="10mm"/>
	</ExportSettings>
</telerik:RadGantt>
  • by using the server-side API of the RadGantt object:
C#
protected void Page_Load(object sender, EventArgs e)
{
	RadGantt1.ExportSettings.Pdf.FileName = "GanttPDF";
	RadGantt1.ExportSettings.Pdf.MarginBottom = "10mm";
	RadGantt1.ExportSettings.Pdf.MarginLeft = "10mm";
	RadGantt1.ExportSettings.Pdf.MarginRight = "10mm";
	RadGantt1.ExportSettings.Pdf.MarginTop = "10mm";
}

See Also