Column Resizing
Updated on Aug 24, 2026
RadGantt allows column resizing. This feature can be enabled/disabled by setting the control's AllowColumnResize property to "true"/"false". To resize a column click and drag a line separating two columns in the TreeList view.
ASP.NET
<telerik:RadGantt RenderMode="Lightweight" runat="server" ID="RadGantt1"
AllowColumnResize="true"
AutoGenerateColumns="true"
SelectedView="MonthView"
Skin="Silk">
</telerik:RadGantt>
The following screenshots show the "Title" column before and after resizing:

For a live example, see Resizing Columns Demo