Is there any way to show a break while we have a very long duration to show in RadGantt?
For eg: when we have 25 years to show in Gantt, is there a way I can just show the first year and the last year with a break indication in between the duration Gantt line?
3 Answers, 1 is accepted
0
Accepted
Bozhidar
Telerik team
answered on 26 Mar 2015, 08:22 AM
Hello,
Currently this is not available in the Gantt control. The control always shows the whole time period occupied by the tasks.
If that is the case, is it possible to remove the sub header? Like if I select Year, I don't want the Gantt to show the Month sub header but only years. This might reduce the longer view a bit.
Removing the bottom headers in not possible, since the Gantt relies on them in order to properly render the timeslots. You can however create a custom view, where only the Years are shown as single headers. I've attached a sample project demonstrating how this could be achieved.