Gantt charting questions

3 Answers 65 Views
Chart (Obsolete)
This is a migrated thread and some comments may be shown as answers.
Ed Staffin
Top achievements
Rank 1
Ed Staffin asked on 05 May 2010, 05:15 PM
Hi,
After spending way too much time looking for an intereactive gantt control, I've given up and am now looking for a static gantt chart.
In particular, will the telerick chart for asp.net support gantting capabilities like milestones, percent complete and task dependencies? If so, is there an example I can look at?
Thanks ... Ed

3 Answers, 1 is accepted

Sort by
0
Ves
Telerik team
answered on 10 May 2010, 09:01 AM
Hello Ed,

I am afraid these are not supported in RadChart. The gantt chart type in RadChart can serve basic purposes like showing task periods.  Please, accept our apologies for not being able to meet your needs.

Best regards,
Ves
the Telerik team

Do you want to have your say when we set our development plans? Do you want to know when a feature you care about is added or when a bug fixed? Explore the Telerik Public Issue Tracking system and vote to affect the priority of the items.
0
M. R.
Top achievements
Rank 1
answered on 14 May 2010, 04:30 PM
Sorry Ves but all these can be done with the radchart control. It's not "out of the box" indeed, you are right, but it can be achieved with proper coding. Just add different series for 'projects', 'percent complete' and 'milestones'.
The 'projects' and 'percent complete' series will be Gantt type, but milestones series will be type 'Point' so that they look as diamonds.
As you can combine together different series and in addition you can add tooltips anp pop-up windows (with a little coding), you should be able to create an interactive Gantt chart.

Regards,
M. Rusu
0
Vladimir Milev
Telerik team
answered on 19 May 2010, 10:08 AM
Hi M. R.,

We apologize for the misleading answer Ves provided. He merely pointed out that the gantt series has some limitations and those features are not included out of the box.

We would like to thank you for helping out your peers with our chart control!

Regards,
Vladimir Milev
the Telerik team

Do you want to have your say when we set our development plans? Do you want to know when a feature you care about is added or when a bug fixed? Explore the Telerik Public Issue Tracking system and vote to affect the priority of the items.
Tags
Chart (Obsolete)
Asked by
Ed Staffin
Top achievements
Rank 1
Answers by
Ves
Telerik team
M. R.
Top achievements
Rank 1
Vladimir Milev
Telerik team
Share this question
or