[Solved] current time indicator on Gantt

1 Answer 14 Views
Gantt
Katia
Top achievements
Rank 1
Katia asked on 21 Apr 2026, 01:49 PM

Hi,

I am building a fleet management planning application using the Telerik Blazor Gantt component. I would like to display a vertical line or marker on the timeline to indicate today's date, similar to a "current time indicator" that visually separates past and future tasks.

I can't seem to find a feature like this in the documentation ? If not, is there a recommended workaround to achieve this ?

Thank you in advance for your help.

1 Answer, 1 is accepted

Sort by
0
Accepted
Dimo
Telerik team
answered on 22 Apr 2026, 06:17 AM

Hello Katia,

A current time marker in the Gantt will be implemented in the future, but I am afraid it's not available now. I voted on your behalf to bump the request priority.

A potential workaround is to render an absolutely positioned vertical line over the Gantt. This will require custom logic and JavaScript-based size and position calculations.

Regards,
Dimo
Progress Telerik

Love the Telerik and Kendo UI products and believe more people should try them? Invite a fellow developer to become a Progress customer and each of you can get a $50 Amazon gift voucher.

Tags
Gantt
Asked by
Katia
Top achievements
Rank 1
Answers by
Dimo
Telerik team
Share this question
or