Hi,
I'm trying to figure out the range snapping when dragging a task in the Gantt timeline. I'm looking to implement a method to snap the task to the start of the day and not show any hours or minutes when dragging the start or end of the task.
Is there a way to customize the tooltip shown while dragging a task? (circled in red in the following screenshot)
I noticed the RangeSnapTo setting for the Gantt in the API reference, but that had no effect on the snapping behavior when dragging the task, or when dragging the start or end of the task. Am I missing something here?
The actual effect I'm trying to achieve is snapping to business days, so Saturdays and Sundays are ignored, but still visible as days in the Gantt chart. Any tips on how to achieve such behavior?
Kind Regards!
Hi Lennert,
As far as I can understand the desired scenario actually targets three requests (please advise if I am missing something):
I've raised a discussion for all these concerns, so we can consider them with the team. I will get back to you to provide details as soon as possible.
Thank you for your patience in the meantime!
Side note: The RangeSnapTo setting targets the starting point of the Gantt Timeline view. More details on that you can find in the Zoom for the Gantt Timeline article.