How can I change for format of dates in Gantt Timeline Views.  For instance, to change to dd/MMM/yyy format?  Seems to default US format.

1 Answer, 1 is accepted

Sort by
1
Hristian Stefanov
Telerik team
answered on 24 Aug 2021, 05:06 PM

Hi Steve,

We have an open feature request for a Functionality for changing the format of the date in the Gantt Timeline:

https://feedback.telerik.com/blazor/1532899-add-functionality-for-changing-the-date-format-in-the-gantt-timeline

This feature would allow you to achieve the desired scenario.

We prioritize feature requests based on community interest. I added your vote there on your behalf to increase the priority of the item. You can also follow the item to get notified via email over status changes.

I can confirm that we are not aware of any workarounds in the meantime for changing the date format.

Please let me know if you have any other questions.

Thank you.

Regards,
Hristian Stefanov
Progress Telerik

Love the Telerik and Kendo UI products and believe more people should try them? Invite a fellow developer to become a Progress customer and each of you can get a $50 Amazon gift voucher.

Tags
Gantt
Asked by
Steve
Top achievements
Rank 1
Veteran
Answers by
Hristian Stefanov
Telerik team
Share this question
or