Andrew asked on 06 Oct 2012, 11:03 PM
I'm trying to change the scheduler to add an option to change all occurrences in a series OR to change just this and future occurrences. The problem I just ran into is that when you select "edit all" it opens the parent schedule item and I cannot seem to find any reference to the date of the occurrence that was selected to actually make the change. Is there a way to get this?

Thanks!

2 Answers, 1 is accepted

Sort by
0
Andrew
Top achievements
Rank 1
answered on 10 Oct 2012, 11:39 PM
I hope this wasn't such a stupid question it didn't warrant an answer. :)
0
Accepted
Plamen
Telerik team
answered on 11 Oct 2012, 07:31 AM
Hello Andrew,

 
You can use the OnClientRecurrenceActionDialogShowing client event to get the start time of the Appointment that is clicked and save it to a HiddenField value that may be used in your further custom logic. 

Hope this will help you.

Greetings,
Plamen
the Telerik team
If you want to get updates on new releases, tips and tricks and sneak peeks at our product labs directly from the developers working on the RadControls for ASP.NET AJAX, subscribe to their blog feed now.