Is there any way to mark a Gantt task as a certain percentage complete?
I would like to see a visual indication in the gantt chart for the percentage...perhaps some type of shading or options to fill the chart with color via brush, etc. to visually indicate a percentage complete.
Thanks, nelson
1 Answer, 1 is accepted
0
Accepted
Masha
Telerik team
answered on 12 Jul 2012, 12:43 PM
Hi Nelson,
Tasks in RadGanttView already support this feature. You can use the Progress Property of the tasks to visualize the task progress.