This is a migrated thread and some comments may be shown as answers.

individual startdate enddate starttime endtime

1 Answer 39 Views
Scheduler
This is a migrated thread and some comments may be shown as answers.
Mike
Top achievements
Rank 1
Mike asked on 17 Mar 2011, 02:46 AM
The schedular requires

DataStartField

 

 

="startDate" DataEndField="endDate"

However our data has a seperate starttime and endtime column. Is there a way to utilize the individual columns of data or does the info need to be combined?

Thanks
Mike

 

1 Answer, 1 is accepted

Sort by
0
Veronica
Telerik team
answered on 17 Mar 2011, 09:13 AM
Hi Mike,

Basically the date and time must be combined to bind the DataStartField and DataEndField.

However as a workaround you can query the two fields and combine them. Please take a look at this link for an example.

Please let me know if you have further questions.

Kind regards,
Veronica Milcheva
the Telerik team
Tags
Scheduler
Asked by
Mike
Top achievements
Rank 1
Answers by
Veronica
Telerik team
Share this question
or