This is a migrated thread and some comments may be shown as answers.

Gantt - Translate, date format, spinbutton increase

1 Answer 66 Views
Gantt
This is a migrated thread and some comments may be shown as answers.
Daniel Aquere
Top achievements
Rank 2
Daniel Aquere asked on 11 Apr 2016, 05:55 AM

Hi Telerik Team,

Pls, I have some issues - see attached image.

1. When I edit a task in a window, how to translate the text "Assign"?

2. When I edit % complete in a row or in a window, how to change for spinbutton increase one by one, 1% until 100%?

3. In gantt header how to change the date format to "dom 03/4 - sáb 16/4"?

 

Thanks, Daniel

1 Answer, 1 is accepted

Sort by
0
Nencho
Telerik team
answered on 14 Apr 2016, 06:43 AM
Hello,

1. Regarding your first questions - indeed there seems to be a problem with changing the Assgn text to a preferable one, since it should be manageable using the following:
<Localization AdvancedAssignResources="Do Assign" />
I have forwarded this to our developer team for further investigation.

2. I am afraid that the default step in the percentage increase/decrease is the one that is currently implemented and it cannot be managed via a property or settings.

3. You can change the needed format, using MonthView-WeekHeaderDateFormat or WeekView-WeekHeaderDateFormat properties and set the preferable format.

Regards,
Nencho
Telerik
Tags
Gantt
Asked by
Daniel Aquere
Top achievements
Rank 2
Answers by
Nencho
Telerik team
Share this question
or