Today Indicator
Updated on Aug 27, 2026
The today indicator represents the current date and time in the graphical view of RadGanttView. There are two indicators you can show. One is positioned over the timeline and the other is directly over the graphical view.

You can control which one is visible through the ShowTodayIndicator and the ShowTimelineTodayIndicator properties.
You can also directly access the two indicators:
C#
GanttViewTodayIndicatorElement todayIndicator = this.radGanttView1.GanttViewElement.GraphicalViewElement.TodayIndicatorElement;
todayIndicator.BackColor = Color.Red;
todayIndicator.BackColor2 = Color.Red;
GanttViewTimelineTodayIndicatorElement timelineTodayIndicator = this.radGanttView1.GanttViewElement.GraphicalViewElement.TimelineTodayIndicatorElement;
timelineTodayIndicator.BackColor = Color.Green;
timelineTodayIndicator.BackColor2 = Color.Green;