plannedStartDate

The date at which the Gantt task starts as per the planned schedule. The plannedStart date is mandatory when rendering the Planned vs Actual view in the Gantt.

Example - set the plannedStart date of a task

<script>
var task = new kendo.data.GanttTask({
    id: 1,
    title: "Task1",
    plannedStart: new Date("2014/6/17 9:00"),
    plannedEnd: new Date("2014/6/17 10:00"),
    start: new Date("2014/6/17 9:00"),
    end: new Date("2014/6/17 11:00")
});
</script>
In this article
plannedStart