                                        asked on 04 Feb 2016, 02:20 PM
                                    
                                I would like to show a Gantt chart for 1, 2 or 3 years
Changeable via a dropdown
right now when I display the Gantt chart it shows several year
because there is tasks running over many years
how do I change the range of the view to a period
5 Answers, 1 is accepted
0
                                Hello,
Currently this is not available in the Gantt control. The control always shows the whole time period occupied by the tasks.
Regards,
Plamen
Telerik
                                        Currently this is not available in the Gantt control. The control always shows the whole time period occupied by the tasks.
Regards,
Plamen
Telerik
Do you want to have your say when we set our development plans?
Do you want to know when a feature you care about is added or when a bug fixed?
Explore the 
Telerik Feedback Portal
and vote to affect the priority of the items
0
                                
                                                    Christian Sandöy
                                                    
                                            
    Top achievements
    
            
                
                Rank 2
            
    
                                                
                                                answered on 05 Feb 2016, 08:17 AM
                                            
                                        Is there a way for the control to start at the current date?
                                        0
                                Hi,
By default the described behavior is not supported by the control but one possible way to achieve similar scenario is to use the approach from this dojo page.
Regards,
Plamen
Telerik
                                        By default the described behavior is not supported by the control but one possible way to achieve similar scenario is to use the approach from this dojo page.
Regards,
Plamen
Telerik
Do you want to have your say when we set our development plans?
Do you want to know when a feature you care about is added or when a bug fixed?
Explore the 
Telerik Feedback Portal
and vote to affect the priority of the items
0
                                
                                                    Christian Sandöy
                                                    
                                            
    Top achievements
    
            
                
                Rank 2
            
    
                                                
                                                answered on 08 Feb 2016, 08:47 AM
                                            
                                        Where do I find the databound in mvc control?
                                        0
                                Hello,
You can find it in the events property as it is described in this help topic here.
Regards,
Plamen
Telerik
                                        You can find it in the events property as it is described in this help topic here.
Regards,
Plamen
Telerik
Do you want to have your say when we set our development plans?
Do you want to know when a feature you care about is added or when a bug fixed?
Explore the 
Telerik Feedback Portal
and vote to affect the priority of the items