Hi,
I am facing challenge because of time portion of the date. In milestone task, both start and end date as well as time should be same. However, even if time part is different, it becomes regular task.
Now, if we keep time part for all dates same say 00:00:00, the tasks which has different start and end date shows a day before, because its just start of the next date. we want end date to be inclusive. and also want milestone type task. Do we have any configuration where time part of gantt is not included in calculation? or some other fix?
https://dojo.telerik.com/eFaCoQOk - This has both example dates.