I have reproduced the issue on the demo you have provided in following link:
https://demos.telerik.com/kendo-ui/scheduler/index

1. goto https://demos.telerik.com/kendo-ui/scheduler/index
2. there is a resource "Call Charlie about the project"
3. set its start date as 6/11/2013 1:30 AM and set its end date as 6/12/2013 4:00 PM
4. Then this Resource will not be displayed on the scheduler. So in such cases how we can show resource for the multiple days without using "alldayevent" tab/option.
how can i view such resources which have part of view in business hours?

1 Answer, 1 is accepted

Sort by
0
Neli
Telerik team
answered on 01 Feb 2018, 08:32 AM
Hi Amol,

The described is the default behavior of the Scheduler. By design the Scheduler renders the all day events or the events longer than 24 hours in the "All day" slot. If you need to display  such events without the "All day" slot, you could use a Timeline view. On the linked demo you can find examples of different Timeline views. 

Another possibility is to create a custom view which matches the requirements of the project. Below you can find links with more information regarding creating custom views:
- https://docs.telerik.com/kendo-ui/controls/scheduling/scheduler/how-to/custom-views/custom-view
https://docs.telerik.com/aspnet-mvc/helpers/scheduler/how-to/custom-view

In case you need assistance in implementing Custom Scheduler view, I would recommend you our Professional services. That team is focused on providing implementations, based on specific use case scenarios. Let us know if you are interested in cooperating with that team and we will put you into contact with them.

Regards,
Neli
Progress Telerik
Try our brand new, jQuery-free Angular components built from ground-up which deliver the business app essential building blocks - a grid component, data visualization (charts) and form elements.
Tags
Scheduler
Asked by
Amol
Top achievements
Rank 1
Answers by
Neli
Telerik team
Share this question
or