im building a gantt  chart components right now, and wondering if there is a way to reorder  the task it self to up/down?
i noticed there is an API for RowContextMenu which return a level in there which i believed is the one responsible in ordering the task
however there is no such function or api to exactly do the reordering

thank you

1 Answer, 1 is accepted

Sort by
0
Accepted
Yanko
Telerik team
answered on 08 Aug 2024, 11:14 AM

Hello, Nico,

With the current implementation of the Gannt Chart reordering the rows is only possible through sorting. As for the level property, it only returns the indexes for the parent and current element but their order can not be modified through it. I can suggest logging a feature request in our feedback portal where we monitor the interest over different requests and the most popular ones are implemented in future releases:

Please let me know if I can provide you with further assistance on this matter.

Regards,
Yanko
Progress Telerik

Do you have a stake in the designеr-developer collaboration process? If so, take our survey to share your perspective and become part of this global research. You’ll be among the first to know once the results are out.
-> Start The State of Designer-Developer Collaboration Survey 2024

Tags
Gantt
Asked by
Nico
Top achievements
Rank 1
Answers by
Yanko
Telerik team
Share this question
or