Border/Brush between main tasks?

3 posts, 0 answers
  1. Grzesiek
    Grzesiek avatar
    105 posts
    Member since:
    Jun 2007

    Posted 04 Sep 2019 Link to this post

    Hey,

    Am I able to set some spacing or border/brush line between only main tasks?

     

  2. Grzesiek
    Grzesiek avatar
    105 posts
    Member since:
    Jun 2007

    Posted 12 Sep 2019 Link to this post

    No idea? :-(
  3. Vladimir Stoyanov
    Admin
    Vladimir Stoyanov avatar
    707 posts

    Posted 16 Sep 2019 Link to this post

    Hello Grzesiek,

    Thank you for the provided picture. 

    I am afraid that the desired functionality is not achievable. This is due to the fact that the cells in the grid portion of the RadGanttView need to be aligned with the rows in the timeline portion of the control, which is by design.

    That said, as an alternative approach I can suggest distinguishing the tasks in some other way. For example, by bolding their titles. You can use a custom CellTemplate in order to change the appearance of specific tasks.

    I hope you find this helpful.

    Regards,
    Vladimir Stoyanov