Hi,
I have two questions I want to ask about your GanttView:
1. For Summary Tasks, is there a built-in way to have the Start and End dates automatically calculate based on the minimum and maximum child dates?
2. Is there a way for certain columns to automatically fill the remaining width of a window. Like the * does in GridView's.
Thanks
I have two questions I want to ask about your GanttView:
1. For Summary Tasks, is there a built-in way to have the Start and End dates automatically calculate based on the minimum and maximum child dates?
2. Is there a way for certain columns to automatically fill the remaining width of a window. Like the * does in GridView's.
Thanks
4 Answers, 1 is accepted
0
Accepted
Hi Peter,
Thank you for your feedback!
Straight to the questions:
1. There is no built-in way to automatically resize the summary. You need to calculate the start and the end date of the summary task each time you manipulate the source collection. We attached a sample project that shows how to achieve this behavior. We will consider including such kind of behavior for the Q1 2013.
2. We have this feature already in our schedule, but it will be not finished for Q3 this year.
I hope this helps you further.
Regards,
Ventzi
the Telerik team
Thank you for your feedback!
Straight to the questions:
1. There is no built-in way to automatically resize the summary. You need to calculate the start and the end date of the summary task each time you manipulate the source collection. We attached a sample project that shows how to achieve this behavior. We will consider including such kind of behavior for the Q1 2013.
2. We have this feature already in our schedule, but it will be not finished for Q3 this year.
I hope this helps you further.
Regards,
Ventzi
the Telerik team
Time to cast your vote for Telerik! Tell DevPro Connections and Windows IT Pro why Telerik is your choice. Telerik is nominated in a total of 25 categories.
0

Peter
Top achievements
Rank 1
answered on 19 Sep 2012, 10:31 PM
Thanks Ventzi
0

Andreas
Top achievements
Rank 1
answered on 15 Jul 2014, 05:00 AM
[quote]2. We have this feature already in our schedule, but it will be not finished for Q3 this year.[/quote]
I'm looking for exactly the same. Is autocalc on summary task already available?
I'm looking for exactly the same. Is autocalc on summary task already available?
0
Hello Thomas Roithmeier,
Unfortunately, this feature is currently not implemented.
However, I've logged this feature request in our Feedback Portal where you can track its status and vote to raise its priority.
Regards,
Polya
Telerik
Unfortunately, this feature is currently not implemented.
However, I've logged this feature request in our Feedback Portal where you can track its status and vote to raise its priority.
Regards,
Polya
Telerik