I am trying to use the kendo scheduler for my project, the issue which i am facing is when the start and end time are of different day, then in the day, week and month view those events are not visible. In the timeline view those events are visible
1 Answer, 1 is accepted
0
Ivan Danchev
Telerik team
answered on 03 Mar 2017, 10:02 AM
Hi Mukesh,
When an event is longer than 24h it is considered as an "all day" event by the Scheduler and is automatically moved to the allDaySlot (dojo example). This behavior is by design and is not configurable. A feature request for adding an option to turn this behavior on/off is already logged in our Feedback Portal, so we can suggest voting for it.