Done Tasks remain in View

1 Answer 21 Views
Bug Management
This is a migrated thread and some comments may be shown as answers.
This question is locked. New answers and comments are not allowed.
Peter
Top achievements
Rank 1
Peter asked on 02 Dec 2014, 11:27 AM
Hi,

My view filters to show only Release 'blank' and Release 'Next update'. When changing the Release of a Story, it correctly disappears from the view. However, the underlying tasks remain in the view. How do I make the tasks disappear too ? I cannot assign a release to the tasks.

Regards,

Peter

1 Answer, 1 is accepted

Sort by
0
Liliya
Telerik team
answered on 02 Dec 2014, 04:44 PM
Hi Peter,

When you move story to the next iteration/release, only tasks that are not done would move together with it.
For reporting purposes tasks that are done remain in the iteration/release, in which they have been completed.

Do not hesitate to get back to us if you have any further questions.