Hi All,
We just moved to the Q2, 2011 release and unfortunately getting the layour cycle error for the chart. I traced it and determined that it's a tick point issue. Here is what's going on: data points are correct for the date range specified but when I iterate through the tick points in the collection I noticed that tick points don't match data points anymore. The layout cycle exception is thrown as soon as a tick point is outside of the date range specified. Why are tick points out of wack with data points? In the previous release they were completely in sync. How are tick points calculated? One other observation: when I run in debug mode in VS 2010 it works as expected. I get the error when I run without debugging.
We switched to databinding but that didn't help either.
If we won't figure out what's causing this we'll have to revert back to the previous release but we are making every effort not to. It would be nice to provide more info than just an error number and a phrase for this error.
Thanks for your help,
Cameron