This question is locked. New answers and comments are not allowed.
Hi there,
I am using Project Dashboard and Work Item Manager with visual studio 2012 and TFS.
In Project Dashboard I am trying to get the above widgets to display meaningful information, unfortunately, it;s not showing was I was hoping.
What I seem to have is for Remaining Work Trend a straight line value of 31. I was sort of expecting to see a downward trend line showing my ideal completion and then another line showing the remaining effort for tasks that are not complete in the sprint.
For Team velocity, I was hoping I could see our velocity of say the last 6 sprint on homw many story points we completed (well I'm using the SCRUM template I think it is so it is effort points were completed)
These 2 metrics are key to Agile planning and monitoring and based on a previous post it was more about the way things were configured/used in TFS.
Is this possible and if I'm doing something wrong could someone point me in the right direction please.
I am using Project Dashboard and Work Item Manager with visual studio 2012 and TFS.
In Project Dashboard I am trying to get the above widgets to display meaningful information, unfortunately, it;s not showing was I was hoping.
What I seem to have is for Remaining Work Trend a straight line value of 31. I was sort of expecting to see a downward trend line showing my ideal completion and then another line showing the remaining effort for tasks that are not complete in the sprint.
For Team velocity, I was hoping I could see our velocity of say the last 6 sprint on homw many story points we completed (well I'm using the SCRUM template I think it is so it is effort points were completed)
These 2 metrics are key to Agile planning and monitoring and based on a previous post it was more about the way things were configured/used in TFS.
Is this possible and if I'm doing something wrong could someone point me in the right direction please.