This question is locked. New answers and comments are not allowed.
Hi all,
I'm currently in a sprint with 6 stories.
Total of 86 task and 15 are done.
If i go to the dashboard and select the correct sprint it tells me that I only have 10 tasks and none are done.
Can someone explain what I do wrong or what i should check to find the problem?
I'm currently in a sprint with 6 stories.
Total of 86 task and 15 are done.
If i go to the dashboard and select the correct sprint it tells me that I only have 10 tasks and none are done.
Can someone explain what I do wrong or what i should check to find the problem?
6 Answers, 1 is accepted
0
Hi Rick,
Is it possible that those tasks has been made done in the previous iteration and after that you changed the iteration of the story?
We made that behavior because we want to show it work that has been done in previous iteration.
the Telerik team
Visit our Ideas & Feedback portal to submit a feature request, vote on existing requests or submit general feedback.
Is it possible that those tasks has been made done in the previous iteration and after that you changed the iteration of the story?
We made that behavior because we want to show it work that has been done in previous iteration.
Greetings,
Jordanthe Telerik team
Visit our Ideas & Feedback portal to submit a feature request, vote on existing requests or submit general feedback.
0
Rick
Top achievements
Rank 2
answered on 19 Sep 2012, 01:37 PM
Hi Jordan,
No we first added the stories to the itteration. Then used the new template functionality to add base steps. After that the team added more tasks and estimates before we started the sprint.
But we did had some syncronization problems for the sprint with TFS. Some how I ended up with 2 times the same itteration. I moved all the stories to the correct sprint and removed the other. This might have caused the problem but I'm not sure.
Is there a way that i can check the SQL database? Because somehow I need to fix the dashboard...
Regards
No we first added the stories to the itteration. Then used the new template functionality to add base steps. After that the team added more tasks and estimates before we started the sprint.
But we did had some syncronization problems for the sprint with TFS. Some how I ended up with 2 times the same itteration. I moved all the stories to the correct sprint and removed the other. This might have caused the problem but I'm not sure.
Is there a way that i can check the SQL database? Because somehow I need to fix the dashboard...
Regards
0
Kees
Top achievements
Rank 1
answered on 20 Sep 2012, 07:54 AM
Maybe stories have moved from on iteration to another, but in general we have this problem.
The tasks are open and connected to stories that are part of the sprint, but the number of tasks are not right as well as the estimate etc.
The tasks are open and connected to stories that are part of the sprint, but the number of tasks are not right as well as the estimate etc.
0
Kees
Top achievements
Rank 1
answered on 20 Sep 2012, 09:01 AM
Jordan
It is not a solution.
Stories can move from sprint to another sprint (while open) with their tasks (while still open)
But in the reporting it is not updated.. it just doesn't represent the truth.
In a simple sample project with for example 3 sprints and 10 stories spread around 3 sprints with all 3 tasks you will see that once you move something .. the whole reporting is broken.
Please solve it and release a hotfix.. so we can start using the reporting part .. which is now useless
It is not a solution.
Stories can move from sprint to another sprint (while open) with their tasks (while still open)
But in the reporting it is not updated.. it just doesn't represent the truth.
In a simple sample project with for example 3 sprints and 10 stories spread around 3 sprints with all 3 tasks you will see that once you move something .. the whole reporting is broken.
Please solve it and release a hotfix.. so we can start using the reporting part .. which is now useless
0
Hello Kees,
All the best,
Jordan
the Telerik team
Visit our Ideas & Feedback portal to submit a feature request, vote on existing requests or submit general feedback.
You initial problem should be related to the changes you've made to fix the sync issue with the second iteration. Most probably the story and task iterations become out of sync.
Can you execute the following script and tell us the result?
You lost your history because you've create a new iteration with the same name and you've deleted the original one. In our history we keep the id of previous iteration and even if the names match the data that we have is for the deleted iteration.
-- Get your current iteation
-- Replace 'Iteration 2' with 'AX2009 Member Portal V1.1' and ProjectID 27 with 26
DECLARE
@iteration
int
SET
@iterationID = (
SELECT
TOP
1 IterationID
FROM
Iteration
WHERE
Name
like
'Iteration 2'
and
ProjectID = 27)
SELECT
@iterationID
-- Select the tasks that has different iterations
DECLARE
@tasks
TABLE
(id
int
)
INSERT
INTO
@tasks(id)
SELECT
Task.TaskID
FROM
Task
inner
join
Story
ON
Task.ParentID = Story.StoryID
WHERE
Task.ParentType =
'Story'
and
Task.IterationID != Story.IterationID
and
Story.IterationID = @iterationID
SELECT
*
FROM
@tasks
UPDATE
Task
SET
IterationID = @iterationID
WHERE
TaskID
IN
(
SELECT
id
FROM
@tasks)
All the best,
Jordan
the Telerik team
Visit our Ideas & Feedback portal to submit a feature request, vote on existing requests or submit general feedback.
0
Kees
Top achievements
Rank 1
answered on 21 Sep 2012, 12:21 PM
Hi
This eavening we sheduled to update the database after a backup has made and we can review the result then.
Hopefully a more permanent solution will be available later.
This eavening we sheduled to update the database after a backup has made and we can review the result then.
Hopefully a more permanent solution will be available later.