Sync\Map Task to Task with TFS

2 posts, 0 answers
  1. Adir
    Adir avatar
    4 posts
    Member since:
    Jan 2013

    Posted 20 Nov 2014 Link to this post

    Hello all,
    it seems that the teampulse is not syncing task to task with TFS
    it can map issues to task or Issues to Issues, but not task to task.
    why is it not working?, and do I have an option for it to work?
  2. Ivan
    Admin
    Ivan avatar
    73 posts

    Posted 20 Nov 2014 Link to this post

    Hello Adir,

    Please refer to this thread: http://www.telerik.com/forums/sync-map-task-to-task-with-tfs-c3fe775e31f5.
    Let us continue the communication in one place.

    Regards,
    Ivan
    Telerik
     