Splitting story to a new sprint

2 posts, 0 answers
  1. Ezequiel
    Ezequiel avatar
    36 posts
    Member since:
    Oct 2011

    Posted 03 May 2012 Link to this post


    My team is evaluating TeamPulse to possible adoption.
    We have a story that we're not able to finish in sprint 1 and we want to move to sprint 2 only the tasks that were not finished and to have the history that something was done in sprint 1 and have the same story name/description/etc in sprint 2...

    Is there a way to do that? We found only the option to change story from sprint 1 to sprint 2.

  2. Lora Borisova
    Lora Borisova avatar
    40 posts

    Posted 03 May 2012 Link to this post

    Hello Ezequiel,

    Thank you for your interest in TeamPulse.

    At this point one possible solution for your case is to just move the item from sprint 1 to sprint 2.

    Other possible solution is to create manually a new story, create a relationship between the two stories, move not done tasks to the new story. There are two shortcuts that can help you to do the job.
    1. Quick Linking
    2. Use task templates as Copy & Paste

    We have request for Split functionality on our feedback portal and it is on our radar. Please give it one more vote here: Copy/Duplicate and Split stories.

    TeamPulse team highly appreciates all feedback so if you have some other questions, suggestions or comments, feel free to contact us at any time.

    All the best,
    Lora Borisova
    the Telerik team