This question is locked. New answers and comments are not allowed.
Good day all,
I'm getting the following TFS sync error on some stories:
Work item has invalid fields. (FieldName='Effort' | Value='1' | Status='InvalidNotOldValue')
I thought in the bidirectional syncing if TeamPulse found a discrepancy that it would ask which source to keep and which to update. However, the only option provided is "Ignore Change". How do I resolve this?
Also the following TFS sync error on some tasks:
Work item has invalid fields. (FieldName='Remaining Work' | Value='[null]' | Status='InvalidEmpty')
We are not using the Remaining Work field in TeamPulse yet. How do we get this to sync with TFS if is empty in TeamPulse? I tried setting the field to 0 (zero) on one of the tasks but I get the same error back.
Thanks.
I'm getting the following TFS sync error on some stories:
Work item has invalid fields. (FieldName='Effort' | Value='1' | Status='InvalidNotOldValue')
I thought in the bidirectional syncing if TeamPulse found a discrepancy that it would ask which source to keep and which to update. However, the only option provided is "Ignore Change". How do I resolve this?
Also the following TFS sync error on some tasks:
Work item has invalid fields. (FieldName='Remaining Work' | Value='[null]' | Status='InvalidEmpty')
We are not using the Remaining Work field in TeamPulse yet. How do we get this to sync with TFS if is empty in TeamPulse? I tried setting the field to 0 (zero) on one of the tasks but I get the same error back.
Thanks.