    Dear Forum,

    I'm sure that this is probably a question that has been answered several times before, but I can't seem to find anything in the forum that relate to this. The problem is that several items continue to appear on my time-sheet view even though they are completed and marked as DONE. I remember reading something some time ago that this issue is caused by the stories or bugs not being set to a specific iteration. I've been through this list and marked all of them to a specific iteration, but the items remain.

    Please advise,


  2. Ivan
    Ivan avatar
    73 posts

    Posted 09 Sep 2013 Link to this post

    Hi Tim,

    I'm sorry for the confusion with the Timesheet screen.

    Timesheet shows all items which have an iteration and this iteration has time interval which contains the current week or part of it. In other words if you have a long iteration which continues many weeks and you add items to it the timesheet will show all these items. You can try to reduce the time-span of the iteration to less time (two weeks for example).

    Also if you change an iteration of Bug or Story, all tasks but these marked as Done or Deleted change there iteration. So all the Task marked as Done or Deleted do not change there iteration. This behavior is needed in order the Reports to generate correct data.