Read dependencies from tasks

2 posts, 0 answers
  1. Marc
    Marc avatar
    69 posts
    Member since:
    Jul 2010

    Posted 07 Dec 2016 Link to this post

    Apologies if this is apparent, but if my tasks already contain the parent/child identifiers, what is the best way to populate the dependency datasource with that information. Do I need to make a call back to the server?
  2. Peter Milchev
    Admin
    Peter Milchev avatar
    208 posts

    Posted 09 Dec 2016 Link to this post

    Hello Marc,

    It seems that you are confusing the parent/child task relationship with the dependencies between the tasks. The dataSources for the tasks and the dependencies are different so you should make separate requests for populating each of them. Here are some resources related to the Gantt:
    Regards,
    Peter Milchev
    Telerik by Progress