Gantt Chart -calculate dates for dependant tasks

2 posts, 0 answers
  1. Sathis
    Sathis avatar
    10 posts
    Member since:
    Mar 2013

    Posted 01 Mar Link to this post

    Ability to auto calculate dates for dependant tasks based on upstream change
  2. Bozhidar
    Bozhidar avatar
    1096 posts

    Posted 03 Mar Link to this post


    The gantt widget doesn't provide any automatic calculation of dependant tasks, since we don't constrict the type and number of dependencies that you can set. Thus it's possible to create cycles in the gantt, which are impossible to calculate and manage. 
    The gantt only calculates the dates of parent and child tasks, since by definition the parent (summary) tasks always reflects the start and end dates of its children.