Hi

I don't find any documentation around DST support in the scheduleview control.  During DST transitions, there is a period of invalid hour in the beginning as the clock is advanced and duplicate hours in the end as the clock is reset back to gain the hour. This should be reflected when the time slots are plotted in the control.

For example, in the UK, DST starts on 27th March and ends on 30th October, this year.  I don't see this behavior in the demo when my time zone is set to GMT,  London.

This is applicable to your Date Time controls also.

Can you please check and confirm ?  If this feature is not currently supported, when will this likely to be available ?

Regards
Selva

1 Answer, 1 is accepted

Sort by
0
Rosi
Telerik team
answered on 21 Sep 2011, 10:18 AM
Hi Selvakumar ,

RadScheduleView behaves as MS Outlook application and always shows 24hours days without removing the hours that are skipped during the Daylight Saving Time. Could you give us more information how do you expect RadScheduleView to behave? A screenshot will help us a lot.


Regards,
Rosi
the Telerik team

Explore the entire Telerik portfolio by downloading the Ultimate Collection trial package. Get it now >>

Tags
ScheduleView
Asked by
Selvakumar Savarimuthu
Top achievements
Rank 1
Answers by
Rosi
Telerik team
Share this question
or