This is a migrated thread and some comments may be shown as answers.

Week and Month View Issues

1 Answer 152 Views
Gantt
This is a migrated thread and some comments may be shown as answers.
Matthew
Top achievements
Rank 1
Matthew asked on 09 Jul 2015, 03:49 PM

My Gantt has view options for Week, Month, and Year.  The Year view functions properly, but the others do not.  In the Week view, where dates columns are supposed to begin on 01/01/2015, they begin on 12/29 of the previous year because I am showing work days only and the 29th is the Monday of the week containing 01/01/2015.  The same issue occurs at the end of the timeline view, where the first of January for the next year is shown because it is the Friday of the work week containing 12/31/2015 (where I want my gantt to end).  I would like to know how to start the chart on the Thursday, 01/01/2015, and end it on Thursday, 12/31/2015, without disabling showWorkWeek.

Similarly, the month view does not start and end the way that I'd like, so I'd like to know how to rectify the issue here as well. 

1 Answer, 1 is accepted

Sort by
0
Dimitar Terziev
Telerik team
answered on 13 Jul 2015, 01:26 PM
Hello Matthew,

You could extend the existing Gantt views in order to create custom ones. Please refer to our online documentation showing how to do so.

Regards,
Dimitar Terziev
Telerik
 
Join us on our journey to create the world's most complete HTML 5 UI Framework - download Kendo UI now!
 
Tags
Gantt
Asked by
Matthew
Top achievements
Rank 1
Answers by
Dimitar Terziev
Telerik team
Share this question
or