Stack Rank Field not visible

3 Answers 103 Views
TFS Integration
This is a migrated thread and some comments may be shown as answers.
This question is locked. New answers and comments are not allowed.
Matthew
Top achievements
Rank 1
Matthew asked on 12 Jan 2011, 10:19 PM
Hi there,
    I am having a problem with Stack Rank not being visible in the system. I can see a bunch of other columns, but Stack Rank doesn't seem to be among them. How can I get the stack rank as we use it for prioritisation of tasks.


Regards,

Matt Brunton

3 Answers, 1 is accepted

Sort by
0
Missing User
answered on 14 Jan 2011, 10:53 PM
Hello Matthew,

We do not have stack rank as an available column in TeamPulse. We developed tasks with the intent that every task is as important as another, and that they all need to be completed in order complete the story they belong to.

I understand that you use Stack Rank as the priority, but what do you use the priority of a task for?

All the best,
Jesse Dyck
the Telerik team
0
Matthew
Top achievements
Rank 1
answered on 16 Jan 2011, 07:37 PM
Yep, while I would agree with you for Tasks, we use Stack Rank on our Stories to prioritise them in the backlog. The backlog is defined well in advance and is loaded into TFS early in the project (although occasionally new stories get added and removed). We use the MSF agile template and although we were initially fairly excited about this tool, we pretty much can't use this without the stack rank as we have hundreds and hundreds of stories in our backlogs for most of our projects. How easy is this to add in to the product? Or is it never going to happen and we need to look at other possible tools?


Thanks for you help,

Matt Brunton
0
Ryan
Telerik team
answered on 17 Jan 2011, 11:21 PM
Hi Matthew,

Could you use the Priority field on Stories as your Stack Rank? You can customize the mappings we use to sync TeamPulse and TFS so that the Stack Rank from your User Story in TFS would sync to Priority on Stories in TeamPulse. Would something like this work for you?

Kind regards,
Ryan
the Telerik team
Tags
TFS Integration
Asked by
Matthew
Top achievements
Rank 1
Answers by
Missing User
Matthew
Top achievements
Rank 1
Ryan
Telerik team
Share this question
or