Mark task percentage complete?

2 posts, 1 answers
  1. Nelson
    Nelson avatar
    4 posts
    Member since:
    Apr 2012

    Posted 11 Jul 2012 Link to this post

    Is there any way to mark a Gantt task as a certain percentage complete?

    I would like to see a visual indication in the gantt chart for the percentage...perhaps some type of shading or options to fill the chart with color via brush, etc. to visually indicate a percentage complete.

    Thanks, nelson

  2. Answer
    Masha
    Admin
    Masha avatar
    252 posts
    Member since:
    Apr 2013

    Posted 12 Jul 2012 Link to this post

    Hi Nelson,

    Tasks in RadGanttView already support this feature. You can use the Progress Property of the tasks to visualize the task progress.

    Please check our online example
    http://demos.telerik.com/silverlight/#GanttView/FirstLook

    If needed, you can copy the code behind and use it in your project.

    I hope this will be helpful.

    Greetings,
    Maria
    the Telerik team