Iteration Burndown

3 posts, 0 answers
  1. Stuart Hemming
    Stuart Hemming avatar
    1622 posts
    Member since:
    Jul 2004

    Posted 20 Jul 2011 Link to this post

    Which figure is the iteration burndown chart using for calculating work remaining?  

    -- 
    Stuart
  2. Stuart Hemming
    Stuart Hemming avatar
    1622 posts
    Member since:
    Jul 2004

    Posted 20 Jul 2011 Link to this post

    And why does the actual value hit zero were it does in the attached?

    -- 
    Stuart
  3. Robert Régnier
    Admin
    Robert Régnier avatar
    1 posts

    Posted 20 Jul 2011 Link to this post

    Hi Stuart,

     The burndown chart is using a combination of the story points and the story status.  As the story's status gets changed to one of the Done states, the story is considered complete and it's points are removed from the burndown thereby bringing the burndown line closer to 0.  In your chart, it would seem as though all of the stories in the iteration either had the points set to 0, or were completed, or were moved out of the iteration on July 21st.

    Kind regards,
    Robert Régnier
    the Telerik team