    is it possible to use a gantt view and time bar together?
    when I tried, it came back with some weird results, but perhaps I am doing it wrong, or it just wont work.
    see screen shot.  notice that it thinks the columns are part of the time range.
  2. Miroslav Nedyalkov
    Admin
    Miroslav Nedyalkov avatar
    1718 posts

    Posted 30 May 2012 Link to this post

    Hi Chad,

    It seems that you are placing the GanttView over or inside the TimeBar control and this causes the observed effect. You could refer to this example that demonstrates how to use the ScheduleView and TimeBar control - the GanttView is used almost the same way as the ScheduleView. The demo is for Silverlight, but exactly the same code could be used in WPF as well.

    Hope this helps.

    Greetings,
    Miroslav Nedyalkov
    the Telerik team

    Explore the entire Telerik portfolio by downloading the Ultimate Collection trial package. Get it now >>

  3. UI for WPF is Visual Studio 2017 Ready
Back to Top