Done Tasks remain in View

2 posts, 0 answers
  1. Peter
    Peter avatar
    1 posts
    Member since:
    Dec 2014

    Posted 02 Dec 2014 Link to this post


    My view filters to show only Release 'blank' and Release 'Next update'. When changing the Release of a Story, it correctly disappears from the view. However, the underlying tasks remain in the view. How do I make the tasks disappear too ? I cannot assign a release to the tasks.


  2. Liliya
    Liliya avatar
    18 posts

    Posted 02 Dec 2014 Link to this post

    Hi Peter,

    When you move story to the next iteration/release, only tasks that are not done would move together with it.
    For reporting purposes tasks that are done remain in the iteration/release, in which they have been completed.

    Do not hesitate to get back to us if you have any further questions.