    My team just completed a sprint where we set a story to done, then found out later that the story was actually not done. We moved the story to the new iteration and set the story status to "In Progress". However, in the new iteration, none of the tasks for the story show up on the task board. We eventually found that we had to include the previous iteration in the view in order to see the tasks from that story on the task board, even though the story is now on the new iteration.

    See the attached file to see the bug in the software.
  2. Liliya
    Admin
    Liliya avatar
    18 posts

    Posted 30 Jul 2014 Link to this post

    Hi Mike,

    When Story is moved to the next iteration – only tasks than are not done yet have their iteration updated as well. The reason for this is to be able to plan and track the iteration capacity of the team broken by task estimate.
    The status of the story tasks is not visible on the screenshot that you have sent, so if this is not the case and tasks are not in done status, I would ask you to send more details to research on the issue.

    Regards,