Blank space when no task exists

3 posts, 1 answers
  1. Travis
    Travis avatar
    4 posts
    Member since:
    Jun 2015

    Posted 07 Jan Link to this post

    Hi,

     When I have a chart displayed like so : http://take.ms/ms8e1

     The space on the right is not available for me to drag a task into if I want to, for example I cannot drag and drop one of the tasks to start on 1/10 in the screnshot without first having a task that exists on that timeline, thus expanding the chart area.

    Is it possible to extend the draggable area out several units past the last existing end date ?

  2. Answer
    Dimitar Terziev
    Admin
    Dimitar Terziev avatar
    1266 posts

    Posted 11 Jan Link to this post

    Hi,

    In order to create custom ranges the existing gantt views should be extended, here is a dojo snippet showing how to extend the week view with one year range.

    Regards,
    Dimitar Terziev
    Telerik
     
    Join us on our journey to create the world's most complete HTML 5 UI Framework - download Kendo UI now!
     