This is a migrated thread and some comments may be shown as answers.

Agenda View showing more days than data includes

3 Answers 37 Views
Scheduler
This is a migrated thread and some comments may be shown as answers.
Brad
Top achievements
Rank 1
Brad asked on 16 Jan 2015, 03:24 PM
For this data:


Why does the Schedule show anything on the 16th (see below)? (dataSource.schema.timezone is "America/Los_Angeles")



Thanks,
Brad

3 Answers, 1 is accepted

Sort by
0
Georgi Krustev
Telerik team
answered on 20 Jan 2015, 12:42 PM
Hello Brad,

I believe that something goes wrong with your post, because there are no images or additional information after your question. Could you clarify a bit or provide a runnable demo  that demonstrate the problem ?

Regards,
Georgi Krustev
Telerik
 
Join us on our journey to create the world's most complete HTML 5 UI Framework - download Kendo UI now!
 
0
Brad
Top achievements
Rank 1
answered on 20 Jan 2015, 01:50 PM
I pasted the images, but that must not work.  I've attached images that correspond to the data and the resulting view.

Brad
0
Georgi Krustev
Telerik team
answered on 22 Jan 2015, 12:00 PM
Hello Brad,

I prepared a simple Dojo demo using your JSON and noticed that the agenda displays one additional task on 21st, which seems incorrect. I logged the issue for further investigation. The fix is scheduled for the next service pack of Kendo UI due the mid of February.

For now, you will need to continue using the agenda as it is, because there is no feasible workaround for this behavior.

As a gratitude for your involvement I updated your Telerik points.

Regards,
Georgi Krustev
Telerik
 
Join us on our journey to create the world's most complete HTML 5 UI Framework - download Kendo UI now!
 